Last week's snowstorm caused a pause in hauling from 10/26 - 10/31 due to significant ground saturation.

Hauling will recommence Monday, 11/2, following this weather delay. 

  • Continuation of excavation with 8-10 trucks round-tripping dirt off-site each day. 
  • Estimated completion for this phase of hauling and excavation is on target for 11/8/20.