- There are currently eight (8) trucks hauling dirt off-site, doing 8-10 round-trips per truck as a part of over lot grading and excavation.
- Hauling on Saturday has been halted until utility work in 4th street resumes, in hopes of giving the neighborhood a break.
- We anticipate completing the current excavation activities by mid-July, at which time you will notice a significant reduction in heavy-impact trucking (semi-sized trucks).